Services of engineering for infrastructure projects of the assets of Pol-chuc operation


 IT REACHES OF THE PROJECT

In the assets of Pol-Chuc operation the extraction of crude slight type (ISTHMUS) in the platforms is carried out satellites, of which it is sent by means of marínos ductos to the Pol-A complex in which the Crude separation of in oil and gas is made. The Gas as well, a part is sweetened and another compressed.

 At the moment the capacity of gas production in the Pol-Alfa complex is of 90MMPCSD and with the additional facilities that are tried to incorporate it would elevate the production to the 105MMPCSD.

As far as the light Oil production (ISTHMUS) 160 MMBD take place at the moment and with the additional facilities that are tried to incorporate it will elevate the production to 225 MMPCSD.

 Next the projects and developed activities in this project are enlisted:

  1. Rehabilitation of Combustible Gas heaters in Modules of Pol-A Compression.

  2. Bitter gas cooling in lines of suction of gas of modules in Pol-A Compression.

  3. Study of loosening and ignition (fire) in arrests flames of atmospheric venteos of compression modules.

  4. Facilities of stairs of access (escape route) in the area of disturb low-pressure compressor in Pol-A Compression.

  5. Reinforcing of would support in mall pillow of safety valves of the rectifier 1ra. Stage in temporary Pol-A.

  6. Installation of a Combustible Gas heater for feeding in I disturb machinery of the complex of water injection.

  7. Installation of BY-PASS of the drainage pressurized towards tanks of vents in temporary Pol-A.

  8. Installation of pneumatic starter engines in turbopumps of temporary Pol-A.

  9. Study, analysis and correction by diminution of efficiency of the General gas generators Electric by changes of prevailing wind direction in temporary Pol-A.

  10. Automatization of equipment of pumping of condensed of the system of vents of Discharge and Loss pressure to battery in Pol-A compression.

  11. Installation of the package of combustible gas measurement in equipment of disturb-pumping of temporary Pol-A.

  12. Installation of the package of measurement of condensed and condensed water in line of return of of platform of compression to weather battery.

  13. Preparation of quarter of electrical control and control center of motors "ccm´s" in the platform of Perforation of the Pol-A Complex.

  14. Rehabilitation of electrical canalizations (includes: Electrical conductors) of the Scada system in the Pol-A complex.

  15. Rehabilitation of the system of inner and perimetral lighting system in quarter of electrical control in platforms PTB and PCS of the Iny-A complex.

  16. Rehabilitation of house of machines of the modules of Pol-A compression.

  17. Rehabilitation of house machines of  I disturb generator ELTS.

  18. Relocationn of equipment and main lines and auxiliary for the redimensionamiento of water injection.

  19. Relocation of containers, instrumentalist and electrical factories of personnel in Pol-A compression.

  20. Feasibility of retirement of the rectifier of 2da. Stage in Pol-A compression.

  21. Installation of cranes of pedestal in Habitacionales Platforms of the Pol-A complexes water and injection.

  22. Rehabilitation of the pluvial drainages of the complexes Pol-A and Iny-A

  23. Rehabilitation of the systems of storage of lubricating oil, synthetic oil, oil of heating, desengrasante amine of the Pol-A platform compression.

  24. Rehabilitation of Plants of Treatment of Oily waters PA-8 and PA-9 of the Iny-A complex.

  25. Feasibility study to count on areas of temporary storage of dangerous remainders in the complexes Pol-A and Iny-A.

  26. Infrastructure installation for the sweetening and Sweet Gas compression for recovery improved in the Chic field.

  27. Acquisition installation, Tests and putting in operation of a Slug-catcher and three Coalescedores filters for recovery of condensed in the bitter gas arrival, the complex water injection.

  28. Change of pumps and modification of mall pillow of unloading in temporary Pol-A (crude oil Dehydration RMSO).

  29. Substitution of the heating oil furnace eclipse of the Pol-A platform compression.

  30. Modification of the system of 1ra. Stage of compression by the redesign of compreso in module no. 4 in Pol-A compression.